Beginning Tuesday, 7/13/10, and continuing through Friday, 7/30/10, from 0800-1100 EDT, QTS facility engineers will perform maintenance on a Liebert 8L Load Bank breaker in the Suwanee, GA Data Center. During this event, engineers will remove a load bank breaker from the Liebert 8L system. No interruption to client services is anticipated.
While we have taken every precaution to minimize complications during this event, there exists a certain amount of risk and the possibility of extended service disruption.
We are committed to providing the highest possible level of service; therefore, we strive to increase client satisfaction and productivity through our proactive approach to customer notification. If you have questions or concerns in advance of this event, please contact our Operations Service Center.